Front:
THE FORTH BRIDGE-THE LABOUR OF 5000 MEN (DAY AND NIGHT) FOR 7 YEARS.
ENGINEERS-SIR JOHN FOWLER & SIR BENJAMIN BAKER.
CONTRACTOR SIR WILLIAM ARROL.
Total length of viaducts over 1
Two spans of 680 feet ea.
below high water level, 91
5,000,000.
COST OVER £3,500,000.
miles including approaches. Two clear spans
Highest part above high water level, 361 feet.
feet. Weight of steel used, 51,000 tons.
of 1710 feet ea.
Deepest foundation
Number of rivets,
Back:
BRITISH
MANUFACTURE
Valentine's Series
This space may be used for Communication
VALENTINE'S
is a guarantee
of BRITISH
MANUFACTURE
€